FINISHING
PLASTERING
Plaster is the art of covering rough
walls, lintels, ceiling sand uneven surfaces in the construction of buildings
and other structures. Normally plastering was done to
Ø Improve
the appearance and to provide a true even smooth and finished surface to the
walls.
Ø Cover
the defective workmanship and to cover up the course materials.
Ø To
give suitable ground for white wash, color wash or paint.
Ø Protect
the surface from harmful defects of atmospheric influences.
Ø To
cover up bad porous materials
A mortar of cement: sand is the proportion of 1:6 is usually recommended for plaster at our site for internal and external walls.
SURFACE PREPARATION OF WALLS FOR
PLASTERING
There are quite a lot of preparations to
do before the plastering of walls commence. Surface to be rendered must clean
and free from all dust, loose materials and etc. Before plastering surplus
mortar present on the wall should chipped off. Otherwise the plaster was not
attached to the wall tightly.
The blocks can be
absorb the water in the plaster mixture as it is begin applied to the wall, the
coating of the plaster next to the block work will dry out too quickly and fail
to set. Should increase dampness of the wall before commence plastering.
In the wall plastering process following
steps was followed. In the mixing stage of mortar used special chemical and
called ‘Feb Mix’. By using Feb -mix can obtain more advantages.
FEB MIX
Feb mix is liquid chemical and used to
enhance workability and freeze thaw resistance of mortar. Feb mix is
recommended for use with cement sand mortar both for brick or block lying and
for plastering to achieve superior quality masonry work and renderings.
ADVANTAGES OF FEB MIX
Ø Ultra
stability of air bubble give prolonged resistance to freeze thaw
Ø Uniform
air entrainment in the structure imparts homogeneity of the mortar matrix
Ø Formulation
ensure effectiveness with most type of Portland cement and rough sand
Ø Micro
air bubble minimize tendency to bleed and segregate
Ø Increase
the cohesion of mortar reduce wastage specially during over hand or vertically
plastering
Ø Imparts
a creamy consistency to mortar that help in easier and faster mortar speed Ø Increases coverage of mortar by upto10%.
Pre mix Feb mix with the gauging water at
the required dosage or add directly in to the mix along the water control water
addition carefully as admixture considerably reduced the water demand for the
achieving the required consistency, due to his superior plastering effect. The recommendation dosage of Feb
mix is 70ml to 140ml per 50kg of cement. Site trials with text mixes should be
conducted to determine the optimum dosage. The dosage will vary from following
factor.
Ø Type
of proportion of cement in the mix
Ø Graduation
of sand
Ø Method
of mixing
In our site we used 85 ml of Feb mix for the 50 kg of
cement
PLASTERING PROCEDURE
Ø Corner
of the wall should plaster as it obtain 900 angles. By using string,
tape and with the help of Pithagaraous theorem (3, 4, 5 method) plaster points
were marked.
Ø The
required thickness of the plaster was marked using cement mortar with broken
tile pieces. (15mm)
Ø The
level was maintained using a plumb-bob.
Ø Those
tiles pieces were kept to level the wall surface easily by leveling bar.
Ø The
1:5 cement sand mortar was applied on the wall surface using masonry’s trowel.
Ø Afterwards
the surface was rubbed by leveling bar (straight edge) and a leveled surface was
obtained. Rough wall finishing was done for the exterior wall where as smooth
wall finishing for the interior wall.
TOOLS USED FOR PLASTERING
Ø Straight
edge
Ø Sprit
level
Ø Gauging
trowel
Ø Brush
Ø Plumb
mob
Ø Finishing
trowel
PAINTING
APPLYING OF WALL COMPOUND (External/
Internal)
After finishing plastering wall compounds
are applied to the internal and external walls. Wall compound consists of 50Kg
bags and it should be mixed with water. To mixed compound with water used
drilling machine with steel rod and it’s vary helpful to mixed compound with
water properly. After mixing applied to wall was done by using gauging trowel.
After applying first coat should keep to drying
and then sand papers applied to obtain smooth and even surface. After
doing above procedure second coat was applied and same procedure was done for
the second coat. External wall compound was used for external walls and
internal wall compound to internal walls.
Finally emulsion (for internal walls)
weather shield (External walls) was painted twice on walls. By using roller
brush, and normal brushes emulsion paints are applied to the walls.
Smooth and even surface was obtained by using sand papers.
FLOOR CONCRETING
After completing of the entire plastering
work floor concreting works are began. First we should be backfilled and it
compacting well by using rammer machine and then special treatment to soil is
done. After soil treatment gave the floor concrete level by using the leveling
instrument. As per the drawing requirement we should level the floor.
For Example
Ø If
the tiling floor we have to kept 35 mm leveling drop rather than normal level.
Ø If
it is a rendering floor we have to kept 25 mm drop.
RENDERING WORK
Rendering is the most commonly floor
finishes method. Before start the rendering work the concrete floor must be
clean and chip, wash properly. Until removing the lose particle and dust. Then
the top level of the rendering bed was mark at the corners of the floor area by
using mortar pots. And the thickness of the bed was not less than 20 mm. In our
site we have to face many difficulties due to level variation of the slab and
floor concreting.
Therefore, before
design the finish floor level we have to get the spot level of the slab and
then get the average value for rendering work.
First the skirting was finish. The height
of the skirting was 100 mm and it thickness was 10 mm. Then cement mortar is
laid on the concrete floor. The cement: sand ratio of the mortar was 1:3 is
used for floor rendering. To have a smooth and level the rendering floor
straight edge and trowel were used. After applying cement-sand motor cement
grout was applied on top of it to get required color and smooth, even surface.
The rendered floor should be cured. Can use gunny bag system to curing and
curing is done to prevent the surface cracks and hollows.
SPECIAL TREATMENT TO SOIL (ANTI-TERMITE
TREATMENTS)
After compaction was completed, Starts the
anti- termite works to areas where concreting workers has to be done. In Digana
housing project used Biflex 10 TC Chemical for that work. Mix proportion should
be 1 -1.5 chemical in to the 100 liter part of the water
First they make the holes of compacted area by using drill machine; depth should not be less than 1ft. Distance in between two holes should not be less than 1 m. Then Biflex 10 TC mixture pressed in to the holes and floor area by using the spray machine. Then by using the polythene sheet covered the treatment areas and then concreting workers done.
TILING
Tilling is used as a floor finishing
method to get aesthetic appearance. And also it is durable & easy clean up
finishing method. Before starting the tiling work following item should be
completed
Ø Apply
paint first coat
Ø Fixing
ceiling grids
Ø Complete the plumbing work
TOOLS USED FOR TILING
Tile Cutter -
Tile cutter used to cut the tile pieces for relevant area
Grinder -
Grinderies used to grind the tile edges and cut the pieces
Rubber hammer And - Leveling the
tile and, to fixed to the better way Spirit level
Scraper -
To apply mortar on the tile bed and tile
ADVANTAGES OF USING TILING
• Stain resistant
• Waterproofing
• Crack
resistant
• Dirt
resistant
• Easy
water clean up
• Suitable
for indoor & out door work
• Anti
fungus
TILING PROCEDURE
Ø Mark ed the tile bed level on the concrete slab
Ø According
to that 1:3 cement sand tile bed was done on the concrete slab Ø On top of the tile bed cement slurry was used & tiles
were placed on top of it.
Ø 5mm
spacing was kept between tiles.
Ø Using
sprit level check the horizontality
Ø Rubber
hammer was used to fix the tiles
Ø After
that Polymer modified hydraulic cement grout was used in the spacing
Ø Rubber
float was used to apply that grout in to the joints & to remove the excess
grout from the surface of the tiles
Ø After
24 hours a soft dry cloth was used to clean up the grout haze
Figure9.1: Floor Tiling
GROUTING
The grout was mixed with clear water to
get a thick foam Then the grout was applied around the all joints and empress
firmly in to gaps. Excess grout should be wiped out with the sponge or cloth.
The floor was left to harden grout for 24 hrs before walking on the surface.
The correct tools for tiling and grouting must be used to
obtain good results.
DURRA BOARD CELLING
Durra bo
ard is unique solid building panel
manufacture from densely compressed rice straw using extreme pressure and heat
in manufacturing process. A variety of surface finishes may be applied on durra
board to suit specific application
PRODUCT FEATURES
• High
quality
• Cost
saving
• Speedy
simple installation
• Reduce
labour time
• Strength
and durability
• Sound
absorption
• Thermal
resistance
• Fire
resistance
• Impact
resistance
• Self
supporting no form work
Table 10.1: Product features of Durra Board
Thickness |
50mm-58mm |
Width |
1187mm |
Length |
2400 & 2700 |
Impact resistance |
2.36 MPa |
Weight |
18.5 kg |
Fire resistance |
1 Hr |
0 Comments