Form Work

  Formwork 



 Column Formwork 

Conventional formwork was used to column formwork. It was fixed to 200 mm height kicker for maintain average pouring height of 1800 mm during the concreting of each element. The formwork box was made with 15 mm thick coated plywood and 50 mm × 50 mm wooden battens. 6 mm sponge sheet layer was kept around the perimeter of the column kicker to stop the grout leakages. Then GI pipes were fixed to the formwork with form ties from four sides of the column. 

 

Formwork was kept steady and vertically using Acro jacks, GI pipes, T jacks, U jacks and necessary props. If jacks were not suitable for the location of the column, High Tension Cables and 300 mm Turn Buckles were used. (Figure 1.1). 

 

Form oil was applied all formwork inner surfaces, so that it will avoid concrete sticking with planks and will be easy to de-shutter. 



 Verticality Check of the Column Formwork 

When marking the location of the column, we marked another line, which is 200mm off to column marking. 200 mm offsets were drawn at four sides of the column to check the horizontal distance between the outer formwork surface and the plumb line. After finishing the column formwork, a wooden strap was fixed on top of the column box with an extended edge of 200mm from a side. Then a plumb bob was freely suspended at the edge of the strap. (Figure 1.2). 



 

Figure 1.2. Verticality Check 

 

Horizontal distance between                         = offset – plywood thickness 

Outer formwork surface and plumb line (x)      = 200 mm – 15 mm = 185 mm 

Top, bottom and middle readings should be equal in order the column to be exactly vertical. If a deviation in the readings occurs, the adjustable props were used to correct the error. The allowable error tolerance was ± 5 mm up to 1.5 m height and ± 10 mm up to 1.5 m to 15 m height. 

 Like that two numbers of vertical faces are checked for vertical alignment; in each faces two numbers of center plum bobs were fixed. 

 

 Slab Formwork 

In slab formwork, before placing beam bottoms we have to mark the +1000 mm level from floor in columns. Then using general arrangements of the slab, the levels and heights were identified. According to those levels, column kickers were placed. (Figure1.3). 



 

       Figure 1.3. Column kicker                                             Figure 1.4. Beam bottom 

Column head level = Floor to floor height – Beam height – Plywood thickness – 1000mm 

 

After that, beam bottoms were placed on 50mm × 50mm timber of kickers and bottoms were aligned to correct locations using plumb bob and offset lines. (Figure 1.5). Then, beam bottoms were levelled using nylon rope and bottom heights were adjusted using acro jacks, T jacks, U jacks.  



 

Figure 1.5. Beam Bottoms Placing 

Beam side board height was calculated using beam heights and slab thickness. Depending up on the beam height, number of P cones for horizontal plane can be decided. One P cone row for beam height up to 750 mm and above 750 mm height beams more than one rows used. Horizontal distance between P cones should be around 900mm for beam height up to 750mm beams and around 600mm for beam height is more than 750mm beams. All beam side boards were brazed using GI pipes and form ties to get proper strength of formwork as well as to maintain the alignment.  

 

For slab panel, 50mm GI pipes were laid around 250mm center to center measurement on the 100mm × 100mm timber planks which was laid on U jacks with scaffoldings. Also 50mm × 50mm timber lining was done with parallel to GI pipes for 15mm plywood board joining. 

Nailing of 8’ × 4’ size of the plywood board will be done to above that timber. Finally, plywood boards were laid on the GI pipes. (Figure 1.6) 



 

  

Figure 1.6. Slab formwork arrangement 

  Slab Formwork Levelling  

Before concreting we checked the levels of slab formwork and beam formwork by using a level machine and followed the inverted staff method.  

 

Firstly, Tripod was setup where can focus previously marked +1000 mm level. Catches were released on each leg and extend and close the catches of tripod. Then legs were spread well apart, with the level plate about chest level of the person who will be reading the levels. After that, level instrument was placed on the base plate and it was attached to the central screw. (Figure 1.7)  

 

The telescope was turned to the parallel to two of the foot screws and levelled off by adjusting the two foot screws simultaneously turning them in opposite directions until the level bubble is central. Then, the telescope was turned 90°, so the telescope points towards the third foot screw and use that third screw to adjust the bubble is central along this axis. Finally, level was checked again in all directions.  


 The telescope was focused on previously marked +1000 mm level line on a column. Since it was difficult to align the level line with the cross line on the telescope. A 5 m steel tape was placed in line with the level line vertically upwards and obtained the reading. For more accuracy, 100mm line in the tape was kept in touch with the level line. After that, inverted staff was kept vertically touching plywood board of the beam or panel. 

Beam levels and slab levels were calculated using general arrangement drawings. (Figure 1.8) If the inverted staff reading was lesser than actual level, the jacks were tight to get the actual level. If the reading higher than actual level, the jacks were loosened to get the actual level. 

Slab level (X) = floor to floor height – machine height – slab thickness – plywood thickness  

                          +3mm (assume when applying concrete load, this will be reduce)  

 

Beam level (Y) = floor to floor height – machine height – beam height – plywood thickness  

                          +3mm (assume when applying concrete load, this will be reduce)  

 

 

 

 

 

 De-Shuttering of Formwork  

Properly constructed forms require little effort to remove them. The only tool that used to remove was the puller along with a light hammer in addition to a ratchet spanner to release form ties. The normal removing times that we allowed in this site was as follows. (Table 1.1) 

 

Table 1.1. Minimum period for striking of formworks 

 

Structure 

Period of removing time 

1. 

Vertical formwork for column, wall, large beams 

01 day 

2. 

Soffit formwork to slab 

14 days 

3. 

Soffit formwork to beams & Props slabs 

14 days 

4. 

Props to beams 

14 days 

 

 


 

Post a Comment

0 Comments